question

Guillaume V avatar image
0 Likes"
Guillaume V asked Allister Wilson answered

Resources quantity not working

Hello,


I have a problem with my model: I want to acquire x2 resources called "AMR" but on my process flow there's only 1 used.
Could someone help me with my issue please?

FlexSim 19.0.0
flexsim 19.0.0acquire resource
resources-problem.png (109.6 KiB)
· 3
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Allister Wilson avatar image Allister Wilson commented ·

I can't see anything wrong in the screenshot you provided, it shows that 1 token is currently using the resource, which is expected regardless of the acquired quantity.

You can see what was actually acquired on the token itself.

Assuming it is indeed not acquiring the correct quantity, could you upload your model so we can take a closer look?

0 Likes 0 ·
Guillaume V avatar image Guillaume V commented ·

@Allister Wilson


On the Activity Properties on the right I put Quantity as "2.00"
Shouldn't the green number next to the Resource AMR be "2" as 1 token passed this stage?

Thanks

0 Likes 0 ·
Guillaume V avatar image Guillaume V commented ·

Understood, thanks @Allister Wilson

0 Likes 0 ·

1 Answer

Allister Wilson avatar image
1 Like"
Allister Wilson answered

From my previous comment :

it shows that 1 token is currently using the resource, which is expected regardless of the acquired quantity

You only have 1 token using the AMR resource, so it shows 1.


You can see what was actually acquired on the token itself.

For instance, in the below image, 1 token has acquired 2 objects from the Sources resource :

If your model is behaving differently, please upload it so we can take a closer look.



1620243729236.png (45.1 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.