question

Carlos Cesar HA avatar image
0 Likes"
Carlos Cesar HA asked tannerp answered

Dead times

How to calculate the waiting time before the first operation?


FlexSim 20.1.1
flexsim 20.1.1dead times
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
tannerp avatar image
0 Likes"
tannerp answered

@carlos_cesar.ha,

Based on your question, it sounds like you need a scheduling tool. Your best bet is to use a Time Table. You can define when you want machines to be available to perform operations. I'll attach a basic example in which the operators are part of a Time Table, which causes them to only work during certain hours (shifts; 6AM-9AM and 9AM-12PM).

time table and source example_1.fsm


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.