Pull Strategy from 4 Lanes

I have 4 Lanes, and I would like them all to feed one processor. The way I want it to work is to pull 5 tokens from lane 1, process them all.. then 5 from lane 2, 5 from lane 3, 5 from lane 4.. repeat. If there isn't 5 in a lane when it needs to be pulled, after waiting a set amount of time, then just take what's available and move to the next. I'm assuming the best way to to this would be with a list, I'm just not very familiar with them and I'm hoping someone could help me get the logic straight on this? I attached an example model, with no lists added yet.

Pulling From Lanes.fsm

FlexSim 20.2.1
listflexsim 20.2.1
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Ben Wilson avatar image Ben Wilson ♦♦ commented ·

Hi @jimmy.g2, was gilbert.jerald's answer helpful? If so, please click the red "Accept" button on their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·

1 Answer

·
gilbert jerald avatar image
2 Likes"
gilbert jerald answered

@jimmy.g2 · I used push and pull from list option in process flow to model your logic. I have attached the model for your reference have a look at it.

Thanks

Support_pulling-from-lanes.fsm


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.