question

Arun Kr avatar image
0 Likes"
Arun Kr asked Kavika F answered

Different Duration For Task Executors In GIS Module

Is it possible to have different durations for task executors in the GIS module? Is this feature added to the latest FlexSim release?

https://answers.flexsim.com/questions/115480/how-to-set-a-travel-duration-that-follows-a-probab.html

Regards,

Arun KR


FlexSim 22.1.3
gis
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Kavika F avatar image
0 Likes"
Kavika F answered

There's currently no feature for variable durations for task executers in the GIS module, but the developers have made a note about this improvement. I hope the workaround suggested in the other answer's post helps you!

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.