Hello,
i hope some one can help me.
How can i make that the first AGV when it starts takes the straight paht? The reason is on the Queue1 comes the first item to load. The straight path is the shortest way.
Hello,
i hope some one can help me.
How can i make that the first AGV when it starts takes the straight paht? The reason is on the Queue1 comes the first item to load. The straight path is the shortest way.
Disconnect and reconnect this "NextWorkPoint" relationship:
Thank you
You can use WorkForwarding connections, so that the AGV can 'see' the work on the other loop from the point ahead of the intersection.
14 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved