Hello guys, I am looking for help with AGV (TaskExecuter) and connection boxes. In my model for master thesis I need to get from stock 8 boxes and join them behind TaskExecuter. I did process in 3D and processflow where operator goes to the stock, get one box, then goes back to TaskExecuter and all o fit go to the another stock. My question is: How can I do in processflow that opertaror goes to the stock 8 times and engages 8 boxes behind the Taskexecuter.

FlexSim 18.1.2
obr3.png (255.6 KiB)
obr2.png (231.2 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Joerg Vogel avatar image
0 Likes"
Joerg Vogel answered

@Ondřej BG,

You put the load activity into a sub flow and the unload activity into another sub flow. Please look into the attached model at the answer, where a taskexecuter transports more items.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.