question

Candice B avatar image
0 Likes"
Candice B asked Ben Wilson commented

Operator Standard Work

I am creating a simulation for a manufacturing processes and the operator has to complete bench 1, then bench 2 then instead of going to bench 3 he goes back to bench 1 and then after 4 units are completed on bench 2, he proceeds to bench 3.

Is there a way to import the stations order and qty of reputation that an operator should follow in a shift?

FlexSim 20.1.3
flexsim 20.1.3operators assignment
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Ben Wilson avatar image Ben Wilson ♦♦ commented ·

Hi @Candice B, was Parker S's answer helpful? If so, please click the red "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·

1 Answer

Parker S avatar image
0 Likes"
Parker S answered

@Candice B

Yes, the order of tasks, the stations, and quantity processed could be put in something like a Global Table. You could then just reference those values in the table as needed.

Can you post your model? It is easier to help when we can see your model and understand what you are trying to achieve.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.