Hi Everyone,
I am trying unload all the units from tote one by one on conveyor . Currently, only one unit is getting unloaded . Can someone please suggest me , how to unload all units using Runsubflow.
Thank you.
Hi Everyone,
I am trying unload all the units from tote one by one on conveyor . Currently, only one unit is getting unloaded . Can someone please suggest me , how to unload all units using Runsubflow.
Thank you.
Run Sub Flow activity set option > Run Tokens One at a Time
Load activity in Sub Process Flow is unnecessary
Unload activity Parameter for item: token.CartonMono.last or perhaps .first
I have added a delay of 1s to see it a bit better visually.
There aren't some labels necessary anymore. Please check it yourself.
Another option is to run only one token in the subflow and add a decision immediately after the Unload. In the decision condition, check if there are still any items in CartonMono using the logic token.CartonMono.subnodes.length > 0. As long as there are items to unload, the operator will unload them one by one. I have attached the file as an example.
14 People are following this question.
© 1993- FlexSim Software Products, Inc. All Rights Reserved.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.