How to make connectors to other areas of the Process Flow

I remember seing a model at a training where different processes in the Process Flow were connected with bubbles similar to this image which leads to another bubble.

But I can't find the model and I can't figure out how to do this.

1694630488768.png

Here I just use the connector shape but it doesn't work.

Also, how do I connect the start of the arrow to the container and not the tasks itself. When I try I get a bunch or splitterpane errors.

FlexSim 23.2.0
process flow
1694630488768.png (11.4 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Jeanette F avatar image
1 Like"
Jeanette F answered Jeanette F edited

Hello @Patrick Cloutier,

You will make a normal connection between the activities/containers. Then select the connector and you will see an option in the properties to change the type

1694633933693.png


1694633933693.png (21.9 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.