I have three lines with three cranes all operated by one operator. Each line requires the crane to pick from one processor to another. What is the best way to do so? I cannot seem to get the connections right.

FlexSim 23.0.3
crane
· 3
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Kavika F avatar image Kavika F ♦ commented ·

Hi @Makenna A,

It's hard to know how to help without looking at your model. To receive a more accurate solution, please post your model or a sample model that demonstrates your question.

Proprietary models can be posted as a private question visible only to FlexSim U.S. support staff. You can also contact your local FlexSim distributor for phone or email help.

0 Likes 0 ·
Jeanette F avatar image Jeanette F ♦♦ commented ·

Hi @Makenna A,

We haven't heard back from you. Were you able to solve your problem? If so, please add and accept an answer to let others know the solution. Or please respond to the previous comment so that we can continue to help you.

If we don't hear back in the next 3 business days, we'll assume you were able to solve your problem and we'll close this case in our tracker. You can always comment back at any time to reopen your question, or you can contact your local FlexSim distributor for phone or email help.

0 Likes 0 ·
Jeanette F avatar image Jeanette F ♦♦ commented ·

Hi @Makenna A, was Joerg Vogel's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·

1 Answer

·
Joerg Vogel avatar image
0 Likes"
Joerg Vogel answered Joerg Vogel edited

You mean something like that:

Operator_uses_cranes.fsm

operator-uses-cranes.jpg

This is a proof of concept. It is depending on items being able to be transported. You would control the output of sending objects to prioritize the operators work. Coordinated Task Sequence Example 2 is made to transport an item by two operators, but as you see, you can get it work with two different taskexecuter class objects.

You can build a logic doing the same in process flow by synchronize activities.


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.