Hi,

Is there a way to enable deallocate on continue for AGV network control points? The goal is for an AGV behind another AGV to start moving as soon as the one in front starts. "Deallocate When Past Current" requires the one in front to clear the control point before it's deallocated which doesn't work.

FlexSim 22.0.16
agvcontrol pointagv deallocation types
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Jeanette F avatar image
0 Likes"
Jeanette F answered Leo L6 commented

Hello @Leo L6,

You can adjust the Deallocation Types in the AGV Network in the tool box.

1695929788720.png

In this case changing the Center to Leading edge may work for what you want