Secuencia de carga y descarga.

Un proceso de de manufactura donde arriban varias materias primas y las mismas se distribuyen con un solo Transporter a diferentes áreas. Necesito saber como hacer una secuencia primero para la carga y luego para la descarga de estas materias primas. (Son 10 source que surten 10 procesos).

Translation

Loading and unloading sequence.

A manufacturing process where several raw materials arrive and they are distributed with a single Transporter to different areas. I need to know how to do a sequence first for loading and then for unloading these raw materials. (That's 10 sources that supply 10 processes.)

FlexSim 22.2.4
schedule source
· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jeanette F avatar image Jeanette F ♦♦ commented ·

Hi @Ahlex,

It's hard to know how to help without looking at your model. To receive a more accurate solution, please post your model or a sample model that demonstrates your question.

If your model contains sensitive information, you could first toggle your post as private using the "make private" option under your question's "gear" menu. Private questions are visible only to site moderators. You can also contact your local FlexSim distributor for phone or email help.

0 Likes 0 ·
Jason Lightfoot avatar image Jason Lightfoot ♦ commented ·

Hi @Ahlex, was Diego Avila's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always comment back to reopen your question.

0 Likes 0 ·

1 Answer

·
Diego Avila avatar image
0 Likes"
Diego Avila answered

Hola @Ahlex,

Para representar el movimiento de materiales de los sources a los procesadores, es importante ligar el Transporter a tus Sources y habilitar el "Use Transport" en el apartado del Output. De esta forma representamos la carga de material en el Source y la descarga en los procesadores.

1709307562061.png


1709307562061.png (279.7 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.