hello every one hope you are doing well
i have encountred a new probleme in a new model, the main problem is in process flow, there is two activities for two different operators, as it is shown in the image, for these activities a made a token and there is a condition at the end to synchronize both activities(tokens) but for some reason, the process flow won't allow it
the main purpose of the transporter is to make a full cycle with the pallet and to stop in certain points
as you can see in the execution there is a error message that i couldn't solve, which i think is the main problem in my model, if any one have an idea how to solve it i will be much gratfull
thank you in advance
simple_example_probleme_V2_synchronize_probleme.fsm