How do specify the process time using the maintenance event function for OR room turnover of a patient that just left? Rooms will have different turnover times based on surgical specialty. We have turnover time based on surgical specialty in a global table.

maintenance
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Adrian Haws avatar image
1 Like"
Adrian Haws answered

You can define the maintenance process time explicitly or with variables such as label value or global table lookup. You would do so in the location of the surgery. Here's an example: