Hello,

I want to extract product names in the Arrival Sequence I put into my Source,

then in the Processor, I want to lookup process time in Global Table that matches with product names.

I made an arrival sequence and global table thus far. However, when I try to match the labels to assign process time in By Global Table Lookup, I don't know what to write.

If you can give me some advice, I would greatly appreciate it.

Thank you

FlexSim 18.2.3
global tablearrival sequence
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Jacob Gillespie avatar image
0 Likes"
Jacob Gillespie answered

I'm not sure what you named your Global Table, how you set up your Global Table, or what your labels are named but the By Global Table Lookup should be filled out similarly to this:


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.