This is the last question I have for this model. Apologies if this may seem on going, and I truly appreciate all the help I've received.
In the simulation I have a processor called "Tray Sealer". This Tray sealer has 2 queues feeding it, called "TraySealerQueue" and "Reworks". After the flow items leave the "DeviceQtyDist" they all have a label called "WONum". Labels with the same value are distinguished by the same colors. Each color represents a Work Order Number (WONum)
As the simulation runs there will be flow items coming out of the "Final Insp" processor that need to be reworked and sent to the "Rework" queue. My question is;
Is it possible that after the Tray Sealer finishes the current color flow items it is working on, can it then address all the flow items in the "Rework" queue, and resume addressing the "Tray Sealer" queue afterwards?
Example for clarity;
Lets say;
Tray Sealer Queue currently has flow items with the colors yellow, orange, and blue. The Tray Sealer processor is currently addressing just the blue flow items. After it finishes the blue flow items and before moving on to the orange and yellow flow items, can it address all flow items in the Rework Queue? After all items in the Rework Queue has been completed, the processor can go ahead and resume processing from orange and yellow flow items from the Tray Sealer Queue.
What I am trying to represent in real life is. An Operator would be working on a Work Order of "X" number of devices, and at the same time there are devices that need to be re-packaged and are waiting in the Rework queue. Once the operator finishes the current work order, and before moving onto the next work order, they will address all items in the Rework Queue. Once all rework devices have been completed, they can go ahead and resume their current task and move onto the next work order from the Tray Sealer queue.
I think it will make more sense when you run the simulation. Thanks ahead of time!