question

Zuleyma D avatar image
0 Likes"
Zuleyma D asked Joerg Vogel converted comment to answer

Crane

Hello,

How can I programm that crane load an item with operator's help?

In my process crane is activated by the operator is why I need to configurate to work together: operator and crane.

Thanks a lot for your help.

cranestask sequence done by an operator
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Joerg Vogel avatar image
4 Likes"
Joerg Vogel answered

Please look for the keywords "coordinated tasksequence". A synchronize task or activity is responsible for the coordination of more Taskexecuters. They act independently, but in the synchronize events they wait to get to the same locations. Maybe you have to change the speed variables of the different taskexecuters to get the look of an operator managing a crane.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.