Antonio R8 avatar image
0 Likes"
Antonio R8 asked Antonio R8 commented

How to include 'risk' in a model

pretimingjobs-rev2.fsm

I've got a process in which I want to allow for a 10% risk as a whole. I believe I can do this through MTBF MTTR, but in the Down Time I've apply a 10% or a 90% and it does not make any difference. See snapshot and model attached. What am I doing wrong?

img-2986.jpg

FlexSim 19.0.2
risk allowance
img-2986.jpg (2.8 MiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Sebastian Hemmann avatar image
2 Likes"
Sebastian Hemmann answered Antonio R8 commented

It seems as if your model was build in Version 2019.1.1.

As the Name MTBF MTTR it gives the option to add a Time between failures and a down time (time to repair). So the field you are working in assumes a time. The option you chose gives the chance to say in 10% the time is 1 (and now you have to complete it and say what should happen in the rest 90%) between two failures!

But if you want a failure rate of 10 Percent you could do something like:

Uptime = 90

Downtime = 10

· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Antonio R8 avatar image Antonio R8 commented ·

That makes sense and works perfectly. Thanks a lot.