Process flow and statistical distribution

Greetings, I am developing an example where the arrival of products is at a rate of 15 per hour. what statistical distribution can help me there because adding a possion and it does not give me the correct values can you help me correct there

1642180540311.png


and in the process it has a time of 3 minutes now it is only for one hour of simulation but with these conditions I would like to apply more time.

XVC.fsm


FlexSim 22.0.0
simulationdistributions
1642180540311.png (171.8 KiB)
xvc.fsm (28.9 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jeanette F avatar image Jeanette F ♦♦ commented ·

Hi @Luis M44, was Jeanette F's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·

1 Answer

·
Jeanette F avatar image
0 Likes"
Jeanette F answered

Hello @Luis M44,

You can change the arrival style to arrival schedule and then set the arrival times for the 15 flow items for the hour. You can then set the table to repeat and it will repeat every hour as long as the last arrival time is set to be an hour. Note you can set that arrival quantity to be 0 at an hour if you are not wanting a flowitem at that time. The table will repeat after the arrival last time.

1642192047882.png


1642192047882.png (10.0 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.