Hello,
It is an open question but I cannot find anything about this.
I want to create a full pull system in my model. By full, I mean being able to give a demand table that should receive a sink, and then my model giving me when each object should start the process to arrive at such date at the sink.
My problem now is that I have the departure dates of each piece in my model, and I want to know when I should start the fabrication of each of these pieces to fullfil with the departure date.
Anything will be much appreciated to start working on this.