question

shanice.c avatar image
0 Likes"
shanice.c asked Jason Lightfoot commented

Resource Activities

Hello,

In order to let 1 agv receive right to travel in advance, I hope only one agv acquire Resource2 at a time. I use Zone activity before and after acquiring Resource2. But two tokens still entry at the same time.

1654160268198.png

testtraffic-control_0602.fsm

FlexSim 22.1.0
resource
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered

The resource is set to local - so one per task executer. Try changing it to global.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.