Hello,

In order to let 1 agv receive right to travel in advance, I hope only one agv acquire Resource2 at a time. I use Zone activity before and after acquiring Resource2. But two tokens still entry at the same time.

1654160268198.png

testtraffic-control_0602.fsm

FlexSim 22.1.0
resource
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jason Lightfoot avatar image Jason Lightfoot ♦♦ commented ·

Hi @shanice.c, was our answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·

1 Answer

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered

The resource is set to local - so one per task executer. Try changing it to global.