Healthcare staff requirement after primary staff is off schedule?

After 5pm, I am having my one MA be off in the shift schedule. However, how can I designate her tasks in the patient tracks to an alternative resource (member of techs) once she is done for the day? I tried using the "based on simulation time" option in the staff requirement in the patient tracks, but I don't understand how to designate that new staff member in the table.

FlexSim 16.1.0
healthcareresourceflexsim hcstaffschedule
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Matthew Gillespie avatar image
0 Likes"
Matthew Gillespie answered Matthew Gillespie commented

This behavior should be automatic.

If you choose a single staff member the staff requirement should be populate as:

Staff1 of StaffGroup1

Where the of GroupX part is showing the group that will receive requests if the staff member is unavailable.

If you choose the staff group, the requests will be given to anyone available in the group.


staffreq.png (17.3 KiB)
· 6
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Katherine Lourie avatar image Katherine Lourie commented ·

Thanks. The issue is that the staff member that should take over this task is in a completely different resource group.

0 Likes 0 ·
Matthew Gillespie avatar image Matthew Gillespie ♦♦ Katherine Lourie commented ·

In that case you'll want to make an alternate group. You can add alternate groups in the toolbox. Then add the members that make up the alternate group.

You should then be able to select the same staff member, but from the alternate group.

0 Likes 0 ·
staffreq2.png (13.7 KiB)
Katherine Lourie avatar image Katherine Lourie Matthew Gillespie ♦♦ commented ·

Yes, I have been trying alternate groups. I just need one specific member from that alternate group to do the task until she is off. But the alternate group option is just having whichever staff member that is available at that moment do the task. It's after 5pm that the task would be given to the other member.

0 Likes 0 ·