question

qoie200011 avatar image
0 Likes"
qoie200011 asked Julie Weller edited

How to combine material retrieval requests in AGV process flow?

Hello,

I have a question is that, every 5 minutes, the processor sends a request for the AGVs to go to the source, pick up the items, and deliver them to the processor. If multiple processors on the same path send requests simultaneously, the AGV needs to go to the source to load the required quantity of items at a time for all the processors on that path and then transport them to their respective processors. For example, if there are 3 processors on a path and 2 of them send requests simultaneously, one AGV needs to go to the source, pick up the two items, and then deliver them to the respective processors.

Currently, we plan to use advanced AGV process flow, but I'm not sure how to incorporate the above requirements into the process flow and how to configure the processors to send material retrieval requests every 5 minutes.

Any help would be appreciated, thank you!

FlexSim 22.2.0
advanced agv process flowmaterial retrieval requests
· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jason Lightfoot avatar image Jason Lightfoot ♦ commented ·

You should find that if an AGV has capacity it will consider the other pickups when it arrives at the respective work points.

The best thing is to test it out and post your model here if you get stuck.

0 Likes 0 ·
Julie Weller avatar image Julie Weller commented ·

Hi @qoie200011, was Jeanette F's answer helpful? If so, please click the "Accept" button at the bottom of the answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always comment back to reopen your question.

0 Likes 0 ·

1 Answer

·
Jeanette F avatar image
0 Likes"
Jeanette F answered Jeanette F commented

Hello @qoie200011,

What you are asking to do can be learned from completing our tutorials and understanding how the AGV template works.

In the AGV Advanced Template in the Main flow you will see one of the activities says "Do I have capacity?". This decision point checks to see if the AGV has the capacity to load another item and if it does then it checks if there is an item to load at that CP.

1687639332966.png

To change your AGV capacity just select it and change the value in the properties window under the tab Task Executer.

1687639417732.png


1687639332966.png (45.0 KiB)
1687639417732.png (5.1 KiB)
· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

qoie200011 avatar image qoie200011 commented ·

Thanks for your kind help @Jason Lightfoot, @Jeanette F! I will try these out.

And I also wonder if it's possible the processors pull item in a random time intervals when the simulation start? Because I need the processors to start pulling request in a different orders.

Thank you!

0 Likes 0 ·
Jeanette F avatar image Jeanette F ♦♦ qoie200011 commented ·
Hello @qoie200011,

Please follow our best practices and start your new question in a new post.

0 Likes 0 ·

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.