question

DeepTom avatar image
0 Likes"
DeepTom asked Jason Lightfoot commented

Process Flow Confusion

IC Project 3.fsmThere is rack 1 and queue 2. I want to create a condition for transporter 2, instructing it to go to queue 2 first if there are items on queue 2, load it from queue 2 and unload it in queue 3. Otherwise, if queue 2 is empty, it can go to rack 1, load the items, and unload them in queue 3.

Hoping for your support

FlexSim 23.1.4
process flowracktransporter
ic-project-3.fsm (58.8 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jason Lightfoot avatar image Jason Lightfoot ♦♦ commented ·

Hi @DeepTom, was Jason Lightfoot's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always comment back to reopen your question.

0 Likes 0 ·

1 Answer

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered

You don't need a process flow for this - just connect the primary feed to Queue3 input 1 and the secondary feed (rack) to input 2 for the Queue3 to pull with that priority.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.