1.Solutions (the job sequence) must be written in the “Sequence” column of the “Job” global table in the FlexSim model.
2.The global table CMAX will automatically compute the makespan performance after the simulation execution.
3.There are two "queue" because I want to start processing after sorting job sequence.
4.The following are FlexSim model and machine data.
Two Parallel Machine Data.xlsxParallel Machine Scheduling Problem -hw.fsm