question

Raashid Mohammed avatar image
0 Likes"
Raashid Mohammed asked Matthew Gillespie answered

change process time of station point in conveyor

Hi

See attached

I have three station points on conveyor which are part of group1

I have source event triggered on process flow to trigger by object group1

I would like to change the process time in the station points using process flow

for example when box enters one of the station points on conveyor token is created

then I want the token to represent which station point has created it

then change that station point process time from 10 to 20 seconds

Please help

See attached model callgroupobject.fsm

Choose One
stations
callgroupobject.fsm (22.7 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Matthew Gillespie avatar image
1 Like"
Matthew Gillespie answered

In this model I changed the processing time field of the stations to just get the value from its processingTime label. I then set this label in the Assign Labels activity in Process Flow. I also used the Assign Event Object To field on the Event Triggered Source to store off a reference to station that triggered the event.


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.