I'm trying to figure out a way to keep an operator at a task until its complete, even if another task with a higher priority is calling for the operator. Thank you for any input.

FlexSim 17.1.2
task sequenceprioritization
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Joerg Vogel avatar image
0 Likes"
Joerg Vogel answered

As long as the newer tasksequence doesn't contain a preempting value greater than 0, which stands for "Do Not Preempt", the operator stays at his current tasksequence.