Event List for tracking which process flow object acquired/release resource.

How can I track in the logger the order of activities that acquired/release a resource? I'm trying to setup a model to show if the crane priority is x,y,z then this is the order to follow for using cranes for a given scenario. alternate-version-2.fsm

Other (please specify)
Other
resourcesdebug
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Matt Long avatar image
0 Likes"
Matt Long answered

That's not something you'll be able to do using the Event Log. What you'd probably want to do is set up a Wait for Event or Event-Triggered Source that would listen to the Resource or the Acquire/Release activities and then log off the information yourself in a global table.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.