In the HC model, I would like to delay the break of the resource when there is no more people waiting in the queue. How should I do it?

If this queue is a common queue, that is people will come back to this queue after they have completed their other processes. How do I delay the break only if I have patient that are going to the bed waiting in the queue?

many thanks

Daviddelay-in-break.fsm

FlexSim HC 5.3.4
delay activitybreak time
delay-in-break.fsm (119.6 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

David Chan avatar image David Chan commented ·

@Cliff King

Good day. Do you have any idea how to do this?

Thanks

David

0 Likes 0 ·

1 Answer

·
Cliff King avatar image
0 Likes"
Cliff King answered Cliff King edited

There's no automatic way using just the Shift Schedule functionality to delay a break based on a condition that needs to continually be checked. You would need to develop your own modeling scheme for sending staff to a break room when conditions are satisfied. Maybe you can try setting up a Global Process that you kick off with a Start Activity Trigger when conditions are right.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.