Hello,
I'm a new user in FlexSim and I'm facing an issue maybe easy to solve thanks to this comunity.
I'm creating Trucks (tokens) with 2000 packages/truck with the "Schedule Source" process. Then I would like to convert those trucks in packages respecting the repartition of columns A, B and C as visible below.
It means that when the Truck3 arrive, I want to create 2 * 2000 *0.25 packages labeled A, 2 * 2000*0.25 packages labeled B and 2 * 2000 * 0.5 packages labeled C.
To do so I used the Create tokens process with assign labeling by percentage but it's not working accordingly since the number packages created by type (A,B,C) is not the right one...
Any insights ?
Thank you