question

Junyuan S avatar image
0 Likes"
Junyuan S asked Joseph Gillespie commented

Order Picking process went wrong

Hi Folks

The attached model simulates a simple order picking process. The operator will pick 24 items on his way to the combiner. However, whenever I set minimum dwell time below 1, the operator will skip couple racks (orders from component lists), pick up the rest of items and go back to the start point to pick up those he skipped. If I set the dwell time to 1, everything goes perfectly fine but I want this simulation to start at time 0. (I think minimum dwell time might not be the only reason).

Thanks in advance for anyone could help. picking-modification.fsm

FlexSim 19.1.1
order picking
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Joerg Vogel avatar image
0 Likes"
Joerg Vogel answered

Run the model with a warmup time. Let the operator begin his work after the warmup time finishes.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.