question

Raymond F avatar image
0 Likes"
Raymond F asked Raymond F commented

Dashboard Input for Process Times of Stations

Is there a way to have a Dashboard input panel of GUI that would allow me to change the process times of multiple stations? In my included model I would like to do this in stations 1-5.

conveyor-process.fsm

FlexSim 19.2.2
dashboard gui
conveyor-process.fsm (451.9 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Sebastian Hemmann avatar image
2 Likes"
Sebastian Hemmann answered Raymond F commented

Hey,

what I normally do in this case is adding a Global Table that stores the value.

As you can see in the attached example the Global Table can be called from the Station (Station 5) and the value can be set in the Dashboard by using objects from the "Model Input" section of the Dashboards and a link to the Global Table.

22846-conveyor-process-1.fsm


· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Raymond F avatar image Raymond F commented ·

Thank you. That worked awesome.

0 Likes 0 ·