Why there are delay/faster to my feed item to conveyor based on decision point?

My application is to feed item to vertical(item also) in conveyor then the item will move to other conveyor. Can you all help me to synchronize the feeding of item when the vertical is detected in decision point? I was not able to do it.

Trial 2.2.fsm

FlexSim 21.1.0
flexsim 21.1.0
trial-22.fsm (1.9 MiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Ben Wilson avatar image Ben Wilson ♦♦ commented ·

Hi @Adsad D, was Aswadauto 's or jason.lightfoot's answer helpful? If so, please click the red "Accept" button at the bottom of one of their answers. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·
Aswadauto avatar image
0 Likes"
Aswadauto answered

I adjust the setting in the conveyor and it work. Need to disable function fixed interval movement function. This fixed interval movement function make certain location to push the item. This make my item to wait for it. And used virtual length for the curve.


capture.png (19.5 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered Aswadauto commented

You can attached a nework node for the DPs and then unload from the operator once the vertical arrives.

trial-22_jl.fsm


trial-22-jl.fsm (1.9 MiB)
· 6
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Aswadauto avatar image Aswadauto commented ·

I need help on this. I need to load the item to vertical and on DP2 it need to transfer to another conveyor. Based on the answer given, why the item is not load even the vertical arrive?

Sorry, I am still new with flexsim simulation. Maybe I misunderstood.

0 Likes 0 ·
Aswadauto avatar image Aswadauto Aswadauto commented ·
0 Likes 0 ·
Aswadauto avatar image Aswadauto Aswadauto commented ·

Also can removed the conveyor at the end, robot, combiner if item not enough.

0 Likes 0 ·
Jeanette F avatar image Jeanette F ♦♦ Aswadauto commented ·

Hello @Aswadauto ,

Was this post helpful for answering this question too?

0 Likes 0 ·
Jason Lightfoot avatar image Jason Lightfoot ♦♦ Aswadauto commented ·

I think this has been answered elsewhere.

0 Likes 0 ·
Aswadauto avatar image Aswadauto commented ·

Hello @Jeanette F, it actually different question.