I've got 2 questions.The first one is about groups. I've got 2 processors in one group - "Drukarki". I'm doing everything in ProcessFlow, so delay times are in there. My operator's destination ("Przejście do drukarki") is Lowest Content in Group. That means every processor has to have the same time. Is it possible, to set different times in ProcessFlow for these 2 processors (Drukarka1, Drukarka2)? I would like it to look like this:
- Drukarka1: normal(150, 10, getstream(activity))
- Drukarka2: normal(120, 10, getstream(activity))
My second question is about amount of items in processor. "Tunel suszący" should process 4 items "koszulka", not 1 like now. Operator takes item from "Drukarka" and put it in "Tunel suszący". He should have the possibility of adding more items. Every item should be process for 240s. Is is possible to make it happen? I've tried to do it by setting "Max Content" in a "Tunel suszący" but it doesn't work. I'm attaching my model.