Operator complete one task at a time

Hello,

In my model I have given setup time to all processors & Combiners, but operator just place the item on processor and move to other station. I want that if operator pick the part from rack 2 and he places part on processor 1 after that he Should complete the processor 1 task (Setup) and then move to another station.

Please find the attached model for your reference.sample model 02 Jan 2022.fsm

Thank you

FlexSim 23.0.1
operator movement
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jeanette F avatar image Jeanette F ♦♦ commented ·

Hi @Tushar H, was one of Joerg Vogel's or Sebastián Cañas's answers helpful? If so, please click the "Accept" button at the bottom of the one that best answers your question. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·
Sebastián Cañas avatar image
0 Likes"
Sebastián Cañas answered

Hi @Tushar H,

An easy way to get the operator to do the setup before he goes to start another task sequence is to increase the priority of that task within the Processor's properties

1672676086615.png

In this case you could simply increase the priority to 1.


1672676086615.png (34.7 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Joerg Vogel avatar image
0 Likes"
Joerg Vogel answered

You do this in Process Flow or by tagged resources:

Please see this thread or search for “tagged operator“ or “tagged resource”

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.