Traffic Control and Dispatcher objects

Model X.fsmWhy operator 2 in my model does not want to participate in the work and go through the defined path between NN2 and NN5. Have I set something wrong in the Traffic Control or Dispatcher object? I am sending my model in the attachment. Thank you for your answer.

Chris

FlexSim 22.0.9
dispatchertraffic control
model-x.fsm (40.6 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Tomasz MG avatar image
0 Likes"
Tomasz MG answered

Hi,

You have the first available option set on your dispatcher object.

1679164320725.png

This means that the task will go to the first free operator, and the order of checking is according to the order of connection of the dispatchers to the dispatcher object.

Boxes appear in the model every 2 minutes, and then the first operator is always available.

Reducing the Inter Arrival time, for example, to one second, you can see that everything works properly.

Best Regards


1679164320725.png (13.4 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.