Hey everyone,


I was wondering if there was a way to run my simulation for multiple days. The way I have it right now is that it runs from 8-5 and just stops at the end, however, I want it to be continuous so that in the event there is a buildup of boxes from the previous day then the operators can work on it the next day as well.


wcocmodel-2.fsm


Thanks,

Amit



FlexSim 23.0.8
simulation time
wcocmodel-2.fsm (173.7 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Julie Weller avatar image
1 Like"
Julie Weller answered

Hey @Aaupadhye! You can just remove the stop time on the top bar. If you go to the Run Tim and click the drop down, deselect the stop times. You might have to add a down time or worker schedule though so that it acts like the end of a real day!