Is there a way to make processors and operators to finish the process that they have already started after the model stop time?
Is there a way to make processors and operators to finish the process that they have already started after the model stop time?
Based on my system's assumptions the machines have to be empty at the end of the work day and I want to include those objects in the throughput.
Instead of this I would recommend not pulling items that can't be completed before the shift end. You might find this answer helpful.
14 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved