question

Jonathan_Huang avatar image
0 Likes"
Jonathan_Huang asked Jonathan_Huang answered

Add transportation task

Hi everyone

In attached model. I want to make operator 2 transfer flow item from queue 7 to queue 8.

But in process flow. The token doesn't move from Pull from list activity to next activity

1709977429219.png1709977491374.png

Please help me

Thank you!

Rhino 4 - test.fsm

FlexSim 23.1.2
processs flow
1709977429219.png (151.1 KiB)
1709977491374.png (42.5 KiB)
rhino-4-test.fsm (5.2 MiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Sri_vikas K avatar image
0 Likes"
Sri_vikas K answered

Hi @Jonathan_Huang

Ensure pushing the list before pulling it.

1709982801634.png

The list is empty (i.e., there are no values to pull from the list). So it is showing in red

1709982862657.png



1709982801634.png (43.1 KiB)
1709982862657.png (1.6 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jonathan_Huang avatar image
0 Likes"
Jonathan_Huang answered

Thank you Mr Sri_vkas


It worked as my expectation


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.