hello,
we have a single line model and we want to apply the pull system on this model.
Our demand should be 15 units per hour.
how do you add this demand in this single line pull model?
hello,
we have a single line model and we want to apply the pull system on this model.
Our demand should be 15 units per hour.
how do you add this demand in this single line pull model?
I'm not sure if this is what you're looking for. But lists allow for the movement of items in "push/pull" manner. When items arrive you can "push" them onto a list, which can then be pulled from. The "pulling" creates backorders on the list when those items have not yet arrived on the list. Is this along the lines of what you're looking for?
@Sébastien D I saw your model and include the Inter-Arrivaltime do 15 units / hour at Source1 and changed the flow / output from By Expression to First Available in order to start the model. Now you can see the dashboards with production / hour information, I hope that can be helpfull for your model idea and Lean concepts!
6547-eerstetrial-groepswerk-rv01.fsm
Regards.
@Sébastien D close the question if the answer was accepted!
Regards
7 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved