Hello,
Using Process Flow... Would it be possible to execute a flow of loading and unloading only if the destination (a rack) is not full?
Something like this example:
The problem is that it unloads in the rack despite being full.
Many thanks.
Hello,
Using Process Flow... Would it be possible to execute a flow of loading and unloading only if the destination (a rack) is not full?
Something like this example:
The problem is that it unloads in the rack despite being full.
Many thanks.
Hi @Alberto M7,
Using a Decide activity would make the most sense here. You can have a Conditional Decide, which will check to see if the rack is at maximum capacity (in my example, 10).
Then, if not, it proceeds to unload the rack.
12 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved