Why is my release not releasing my resource in my process flow ?

v4.fsm

Hello, I share a model with you in which I try to simulate a task happening in a factory.
At the end of my processflow I try to release a resource called "110 (FDS)".

For some reason the release doesn't seem to be working. Could someone help me understand why?

Gui

FlexSim 19.0.0
processflowflexsim 19.0.0resourcerelease
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered Jeanette F commented

Use batch instead of join activities.