Hi, im creating this model and I´m trying to make an operator to get a box ubicated in the queue near the elevator, so I need to make that the operator lift the box, get in to the elevator and place the box in the floor storage.

The floor storage is elevated, so thats why I´m using the elevator, but I dont understand any logic to make an operator lift and ubicate the box.

Thanks for the help!


1630466666889.png

Choose One
operatorfloor storagechoose one
1630466666889.png (384.0 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Julio R avatar image
0 Likes"
Julio R answered Julio R commented

Hello Dennis,

I understand that you want the operator to use the elevator and not only the box. To do this you need to use the elevator inside the People section of the library.

1630506708895.png

To use the elevator the easiest way is to include Astar with two different floors.

If you need a more detailed explanation please let us know.