Hey guys,

My problem is that i have an multiprocessor who writes"OnProcessFinish" the finished processes into the global table (+1). So when the maximum is reached a message pops up .

Now i want to set up like a traffic light who turns red ,( every time the when the message pops up) and the operator should "change" the maximum on zero again?

Is it also possible to dont stop the flow of the project ? (It hasn't to be a message)

Thanks in advance guys :)

sign.fsm

FlexSim 17.1.2
operatorstopmessagestraffic lightmaximum
sign.png (68.9 KiB)
sign.fsm (18.7 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Raja Sekaran avatar image
0 Likes"
Raja Sekaran answered Sinisa commented

Hi,

I have attached your model with the changes I have made.

In the attached model, when the maximum is reached, I sent a message to indicator object(Dispatcher) to change color of indicator object into red and settable value to zero.

sign-indication.fsm

sign-indication-v1.fsm


capture.png (100.1 KiB)
sign-indication.fsm (19.7 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Sinisa avatar image Sinisa commented ·

Thanks ! appreciate your help

1 Like 1 ·