Roller chute 1.1.fsmGood day. Please see attached model. I want to optimize the walking efficiency of my operator. Currently the roller chute is set as a slug builder so that the operator will only go to unload the roller conveyor chute when there is a minimum of 3 parcels on it. The problem comes in when 2 or 3 conveyors get 3 boxes each at a similar time then the operator walks far distances between each conveyor offloading only one box at a time between long walking distances. How can I make the operator complete the unloading of one roller conveyor at a time to optimize efficiency? Also how can I make the operator prioritize the unloading by distance or conveyor % occupancy? Basically it I want to see how many roller conveyor chutes can be maintained (unloaded) by one operator alone if he is working in the most efficient manner.
Thanks