question

Owen_liaw H avatar image
0 Likes"
Owen_liaw H asked Jason Lightfoot commented

How to set the time table for working and rest

Helo, i have problem on the timetable. How to make with some condition:

1.it have 5 working days (120 hours with 8 hours warm-up)

2. After 5 days of work, the line is completely stopped for a weekend and in the next week a new warm-up is required.

3. Available work time is reduced by cleaning of machine (15 minutes per shift) and a rest pause for operator (15 min per shift) and is equal to 465 minutes per shift for processor and 450 min for operator

4. Hope u can use the date based

1648130215339.png

abc1.fsm

FlexSim 22.0.1
timetables
1648130215339.png (42.4 KiB)
abc1.fsm (34.5 KiB)
· 3
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Joerg Vogel avatar image Joerg Vogel commented ·
Use more time tables for different down states.
0 Likes 0 ·
Jason Lightfoot avatar image Jason Lightfoot ♦♦ Joerg Vogel commented ·

You can change the down state for each stoppage in a single timetable.

1 Like 1 ·
Ryan Clark avatar image Ryan Clark commented ·

Hi @Owen_liaw H, was Jason Lightfoot's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·

1 Answer

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered Jason Lightfoot commented

Timetables are for defining planned unavailability. I would put the operator shifts/ in one timetable and the machine schedule in another. Use the calendar based timetable and add the week's profile as repeating down events - repeating every 7 days where applicable, or for longer (e.g. quarterly) maintenance, add those as individual stoppages.

Attached is an example of how you might set up an operator and machine timetable.

abc1_jl.fsm


abc1-jl.fsm (49.6 KiB)
· 3
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Chris C8 avatar image Chris C8 commented ·
Jason, thank you and this makes sense to me, I will begin to work on this tonight.


I would offer you a reward however you received my only point, i'm sad.


Thanks

Chris

0 Likes 0 ·
Owen_liaw H avatar image Owen_liaw H commented ·
ty for help, but i have the problem about the operator. For example, the operator shift is from 0800am to 0300pm, but he still work when the time is exceed 0300pm


0 Likes 0 ·
Jason Lightfoot avatar image Jason Lightfoot ♦♦ Owen_liaw H commented ·
Can you post the model? I just showed how to represent the times and split it between machine and operators.
0 Likes 0 ·