question

Kimon S avatar image
0 Likes"
Kimon S asked Jeanette F commented

How to control when a list is pulled from? Only pull between working hours.

FlexSim 22.1.2
schedules
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Jason Lightfoot avatar image
1 Like"
Jason Lightfoot answered Jason Lightfoot edited

There will be a number of ways to do this - one of which would be to first pull from a list (leaving entry on the list) that contains an entry when on-shift and does not when offshift. Place your token/item/job pull after the 'onshift' pull. This way you will start immediately when the shift events push to the on-shift list.

Attached is an example that uses the Timetable to push/pull to the Global List - "OnShift"

ProcessFlowShiftExample.fsm


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.