question

John MA avatar image
0 Likes"
John MA asked Julie Weller commented

Object states are not being taken into account

In this example, it can be seen that the "Scheduled Down" status is not plotted when its schedule is active, nor is it taken into account in the "Financial Analysis" statistics that the down status is not accounted for.


I would like that when scheduling the timetable, its status would be plotted and also that in the financial analysis it would only count the time when the machines are in "Idle or Processing" status.


Thank you very much for your help



Simulación 2_1.fsm

FlexSim 23.1.1
statesstate statisticsstatisctis collector
simulacion-2-1.fsm (41.1 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Julie Weller avatar image Julie Weller ♦ commented ·

Hi @John MA, was Sebastián Cañas's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always unaccept and comment back to reopen your question.

0 Likes 0 ·

1 Answer

·
Sebastián Cañas avatar image
2 Likes"
Sebastián Cañas answered Jeanette F commented

@John MA ,
The Scheduled down state is Excluded as default within the State Table.

1684437742201.png

If you want to see that state in any graphic you could either change the Analysis set as Utilized or you can check the option Show Excluded States that you see in the graphic properties.

1684437819665.pngsimulacion-2-1-sc.fsm


1684437742201.png (66.5 KiB)
1684437819665.png (56.1 KiB)
· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

John MA avatar image John MA commented ·

Muchas gracias. Y sabe cómo configurar la herramienta de análisis financiero para que solo tenga en cuenta el costo en los estados inactivo y de procesamiento. es decir, excluye el cálculo del coste por tiempo, mientras se encuentre en el estado Scheduled Down. Porque si nos fijamos cuando comienza la simulación, cuenta el costo de los procesadores que están en programado hacia abajo


Thank you so much. And do you know how to configure the financial analysis tool to only consider cost in the idle and processing states? That is, so it will exclude time costing while in the Scheduled Down state. Because if you look at when the simulation starts, it counts the cost of the processors that are in scheduled down

0 Likes 0 ·
Jeanette F avatar image Jeanette F ♦♦ John MA commented ·

Hello @John MA,

The model Sebastián Cañas posted shows that the financial analysis chart is only taking into account the idle and processing. Select the chart and then select one of the objects in the list of attached objects.

1684947323958.png

Please check out the manual to learn about this properties panel

0 Likes 0 ·
1684947323958.png (17.7 KiB)

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.