Changes the "scheduled down" status temporarily

Changes the "scheduled down" status temporarily while the operation is being completed

Hi Team,

The simulation time will be 4 hours (07:50 a.m. - 12:00 m).

I have a 2 hour work shift (08:00 a.m. - 10:00 a.m.) This shift is scheduled in TimeTable. The other two hours, it will be in "scheduled down" status.

I need them to continue to operate until the inventory in process is completed, despite having a shift specified in TimeTable. How can I do this? Without deleting the scheduled shift.

Thank you so much for the support.

TimeTable.fsm

support-timetable.png


FlexSim 23.1.2
timetablesscheduledow
timetable.fsm (131.5 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered

Any TEs connected to a dispatcher you can close and open inputs instead of stopping the object.

Or you can create a non-preempting utilize task sequence, and call freeoperators on resume.

There are probably too many ways to cover in one post.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.