question

mohammadmajd avatar image
0 Likes"
mohammadmajd asked Jason Lightfoot answered

End the operation after stop time

Is there a way to make processors and operators to finish the process that they have already started after the model stop time?

FlexSim 23.0.7
stop time
· 5
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jason Lightfoot avatar image Jason Lightfoot ♦♦ commented ·
Can you explain why you would wish to do this? It is possible to destroy the events of objects and preempt and abort tasks on task executers but I'd like to know more about your use case, should there be a better solution.
0 Likes 0 ·
mohammadmajd avatar image mohammadmajd Jason Lightfoot ♦♦ commented ·

Based on my system's assumptions the machines have to be empty at the end of the work day and I want to include those objects in the throughput.

0 Likes 0 ·
Jason Lightfoot avatar image Jason Lightfoot ♦♦ mohammadmajd commented ·
Okay but that could also be done by not taking the last item because there's not enough time to process it in the day - and wouldn't that be more realistic?
0 Likes 0 ·
Show more comments

1 Answer

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered

Instead of this I would recommend not pulling items that can't be completed before the shift end. You might find this answer helpful.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.